No Helpers Assigned?

If your first attempt at AutoFilling your schedule leaves your shifts unassigned, please check the following:

1. Are helpers set to work your Positions?

  • In the top menu, hover over HELPERS and choose “Positions Grid” 
  • Check the boxes next to the Positions that this helper can work 
  • Click Save button

2. Are helper maximum hours per day shorter than the “Help Hours” (duration) of the shifts?

To see what your Helpers Maximum Hours per day are:

  • In the top menu, click HELPERS to go to the List Helpers page 
  • Check the Max Hours per Day & Week column (if column is not visible, use the “Select Columns” link in the upper left to add it) 
  • To make a change, click the cell and type the correct number for each helper
  • Click the Save button to save all changes

OR you can click the pencil icon  pencil icon next to the helper name and make the changes in that helper’s Edit Helper window and click Save & Next button to go through the list.

3. Are your Shifts “Help Hours” correct?  

If you added shifts and did not set the Paid Hours, then the shift’s paid hours will be Auto-Calculated, which may result in shift durations that do not include any uncounted break time. The shift duration should be the total paid hours for that shift. 

To see what your shift duration (paid hours) are:

From any page: 

  • In the top menu, hover over SCHEDULES and choose Multi-Shift Edit Weekly view
  • Look at the “Helped Hrs” column which shows the hours worked for each shift
  • Make changes to the shift duration if needed 
  • Click the Save Changes button

 